Restoration of alag river control approach b downstream, Baco, Oriental Mindoro

Tapos na

PUBLISHED NA BUDGET

₱8,710,795

Budget ayon sa dokumento, hindi aktwal na gastos. Published na budget ito, hindi aktwal na gastos, at hindi paratang laban kaninuman.

Mahahalagang datos

Taon
2018
Bayan
Baco
Katayuan
Tapos na
Kategorya
Flood Control and Drainage
Contractor
CMSEL CONSTRUCTION & DEVELOPER
Simula
Mar 8, 2018
Katapusan
Oct 17, 2018
TAGAL
223 araw
ID ng proyekto
18ED0025

ORAS

Timeline

Simula

Mar 8, 2018

223 araw mula simula

Katapusan

Oct 17, 2018

LOKASYON

Nasaan ito

Coordinates: 13.37053, 121.07941

DETALYE

Detalye ng proyekto

Orihinal na pamagat
RESTORATION OF ALAG RIVER CONTROL APPROACH B DOWNSTREAM, BACO, ORIENTAL MINDORO

KATULAD NITO

Mga kaugnay na proyekto

Parehong bayan o parehong uri ng gawain, pinakamalaking published na budget muna.

Source: DPWH Infrastructure Transparency Dataset via BetterGov Open Data (CC0). Ang bayan ay hinuhulaan mula sa coordinates at pamagat. Balik sa lahat ng proyekto.

Tulungan kaming buuin ang site na ito

Ang site na ito ay ginawa at pinapanatiling updated ng mga volunteer mula sa Oriental Mindoro. Sabihin kung paano ka makakatulong.

Gagamitin lang namin ang detalye mo para kontakin ka tungkol sa pagba-volunteer.