Flood control · Brgy. Sta

Construction/rehabilitation of flood mitigation facilities within major river basins and principal river, construction of baroc river control, brgy. sta. brigida section, sta. 0+000 , sta. 0+770, Mansalay, Oriental Mindoro

Tapos na

PUBLISHED NA BUDGET

₱48,996,447

Budget ayon sa dokumento, hindi aktwal na gastos. Published na budget ito, hindi aktwal na gastos, at hindi paratang laban kaninuman.

Mahahalagang datos

Taon
2022
Katayuan
Tapos na
Kategorya
Flood Control and Drainage
Contractor
LUMEL GLENN CONSTRUCTION
Simula
Jun 3, 2022
Katapusan
Mar 9, 2023
TAGAL
279 araw
ID ng proyekto
22EI0018

ORAS

Timeline

Simula

Jun 3, 2022

279 araw mula simula

Katapusan

Mar 9, 2023

LOKASYON

Nasaan ito

Coordinates: 12.57610, 121.48544

DETALYE

Detalye ng proyekto

Orihinal na pamagat
CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVER, CONSTRUCTION OF BAROC RIVER CONTROL, BRGY. STA. BRIGIDA SECTION, STA. 0+000 , STA. 0+770, MANSALAY, ORIENTAL MINDORO

KATULAD NITO

Mga kaugnay na proyekto

Parehong bayan o parehong uri ng gawain, pinakamalaking published na budget muna.

Source: DPWH Infrastructure Transparency Dataset via BetterGov Open Data (CC0). Ang bayan ay hinuhulaan mula sa coordinates at pamagat. Balik sa lahat ng proyekto.

Tulungan kaming buuin ang site na ito

Ang site na ito ay ginawa at pinapanatiling updated ng mga volunteer mula sa Oriental Mindoro. Sabihin kung paano ka makakatulong.

Gagamitin lang namin ang detalye mo para kontakin ka tungkol sa pagba-volunteer.