Concreting of morente - batangan fmr, brgy. morente and batangan, Bongabong, Oriental Mindoro

Tapos na

PUBLISHED NA BUDGET

₱11,517,173

Budget ayon sa dokumento, hindi aktwal na gastos. Published na budget ito, hindi aktwal na gastos, at hindi paratang laban kaninuman.

Mahahalagang datos

Taon
2021
Katayuan
Tapos na
Kategorya
Roads
Contractor
MADSAM ENTERPRISES
Simula
Jul 15, 2021
Katapusan
Dec 31, 2021
TAGAL
169 araw
ID ng proyekto
21EI0187

ORAS

Timeline

Simula

Jul 15, 2021

169 araw mula simula

Katapusan

Dec 31, 2021

LOKASYON

Nasaan ito

Coordinates: 12.67716, 121.37701

DETALYE

Detalye ng proyekto

Orihinal na pamagat
CONCRETING OF MORENTE - BATANGAN FMR, BRGY. MORENTE AND BATANGAN, BONGABONG, ORIENTAL MINDORO

KATULAD NITO

Mga kaugnay na proyekto

Parehong bayan o parehong uri ng gawain, pinakamalaking published na budget muna.

Source: DPWH Infrastructure Transparency Dataset via BetterGov Open Data (CC0). Ang bayan ay hinuhulaan mula sa coordinates at pamagat. Balik sa lahat ng proyekto.

Tulungan kaming buuin ang site na ito

Ang site na ito ay ginawa at pinapanatiling updated ng mga volunteer mula sa Oriental Mindoro. Sabihin kung paano ka makakatulong.

Gagamitin lang namin ang detalye mo para kontakin ka tungkol sa pagba-volunteer.