Flood control · Brgy. Malaya section
Construction/rehabilitation of flood mitigation facilities within major river basins and principal rivers, construction of madugo i river control, barangay malaya section, Roxas, Oriental Mindoro
Tapos na
PUBLISHED NA BUDGET
₱48,997,656
Budget ayon sa dokumento, hindi aktwal na gastos. Published na budget ito, hindi aktwal na gastos, at hindi paratang laban kaninuman.
Mahahalagang datos
- Taon
- 2024
- Bayan
- Roxas
- Katayuan
- Tapos na
- Kategorya
- Flood Control and Drainage
- Contractor
- LUMEL GLENN CONSTRUCTION
- Simula
- Mar 7, 2024
- Katapusan
- Dec 21, 2024
- TAGAL
- 289 araw
- ID ng proyekto
- 24EI0074
ORAS
Timeline
Simula
Mar 7, 2024
289 araw mula simula
Katapusan
Dec 21, 2024
LOKASYON
Nasaan ito
Coordinates: 12.60054, 121.51847
DETALYE
Detalye ng proyekto
- Orihinal na pamagat
- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF MADUGO I RIVER CONTROL, BARANGAY MALAYA SECTION, ROXAS, ORIENTAL MINDORO
KATULAD NITO
Mga kaugnay na proyekto
Parehong bayan o parehong uri ng gawain, pinakamalaking published na budget muna.
Sustainable infrastructure projects alleviating gaps (sipag) flood mitigation structures protecting public infrastructures/facilities- const. of Roxas by-pass road, Roxas, or. Mindoro
IsinasagawaRoxas2023
₱221.9 M
published na budgetFlood control · Brgy. San mariano section
Tapos naRoxas2023
Construction/rehabilitation of flood mitigation facilities within major river basins and principal rivers - construction of baroc river control structure, brgy. san mariano section, Roxas, Oriental Mindoro
₱82.0 M
published na budgetFlood control · Brgy. San aquilino section
Tapos naRoxas2022
Construction/rehabilitation of flood mitigation facilities within major river basins and principal river, construction of baroc river control, brgy. san aquilino section, sta. 0+000 - sta. 0+796, Roxas, Oriental Mindoro
₱49.0 M
published na budgetFlood control · Brgy. San miguel section
Tapos naRoxas2022
Construction/rehabilitation of flood mitigation facilities within major river basins and principal river, construction of baroc river control, brgy. san miguel section, sta. 0+000 - sta. 0+802, Roxas Oriental Mindoro
₱49.0 M
published na budget
Source: DPWH Infrastructure Transparency Dataset via BetterGov Open Data (CC0). Ang bayan ay hinuhulaan mula sa coordinates at pamagat. Balik sa lahat ng proyekto.