Construction of 1 unit 1 sty 2 cl & 1 unit 1 sty 3 cl at Mansalay cs, Mansalay, Oriental Mindoro

Tapos na

PUBLISHED NA BUDGET

₱6,875,701

Budget ayon sa dokumento, hindi aktwal na gastos. Published na budget ito, hindi aktwal na gastos, at hindi paratang laban kaninuman.

Mahahalagang datos

Taon
2018
Katayuan
Tapos na
Kategorya
Buildings and Facilities
Contractor
AIDFELART CONST. CORP.
Simula
Jan 21, 2019
Katapusan
Jun 29, 2019
TAGAL
159 araw
ID ng proyekto
18EI0163

ORAS

Timeline

Simula

Jan 21, 2019

159 araw mula simula

Katapusan

Jun 29, 2019

LOKASYON

Nasaan ito

Coordinates: 12.52121, 121.44053

DETALYE

Detalye ng proyekto

Orihinal na pamagat
CONSTRUCTION OF 1 UNIT 1 STY 2 CL & 1 UNIT 1 STY 3 CL AT MANSALAY CS, MANSALAY, ORIENTAL MINDORO

KATULAD NITO

Mga kaugnay na proyekto

Parehong bayan o parehong uri ng gawain, pinakamalaking published na budget muna.

Source: DPWH Infrastructure Transparency Dataset via BetterGov Open Data (CC0). Ang bayan ay hinuhulaan mula sa coordinates at pamagat. Balik sa lahat ng proyekto.

Tulungan kaming buuin ang site na ito

Ang site na ito ay ginawa at pinapanatiling updated ng mga volunteer mula sa Oriental Mindoro. Sabihin kung paano ka makakatulong.

Gagamitin lang namin ang detalye mo para kontakin ka tungkol sa pagba-volunteer.