Cluster xvii: 1.) construction of 1 storey / 4 classroom at jose l. basa memorial school, Naujan 2.) construction of 1 storey / 4 classroom at jose l. basa memorial school, Naujan 3.) construction of 1 storey / 4 classroom at jose l. basa memorial school,

Tapos na

PUBLISHED NA BUDGET

₱15,706,662

Budget ayon sa dokumento, hindi aktwal na gastos. Published na budget ito, hindi aktwal na gastos, at hindi paratang laban kaninuman.

Mahahalagang datos

Taon
2017
Bayan
Naujan
Katayuan
Tapos na
Kategorya
Buildings and Facilities
Contractor
GREAT LAKES ENTERPRISES (31429) / FRAMECON BUILDERS
Simula
Jan 11, 2018
Katapusan
Aug 15, 2018
TAGAL
216 araw
ID ng proyekto
17ED0170

ORAS

Timeline

Simula

Jan 11, 2018

216 araw mula simula

Katapusan

Aug 15, 2018

DETALYE

Detalye ng proyekto

Orihinal na pamagat
CLUSTER XVII: 1.) CONSTRUCTION OF 1 STOREY / 4 CLASSROOM AT JOSE L. BASA MEMORIAL SCHOOL, NAUJAN 2.) CONSTRUCTION OF 1 STOREY / 4 CLASSROOM AT JOSE L. BASA MEMORIAL SCHOOL, NAUJAN 3.) CONSTRUCTION OF 1 STOREY / 4 CLASSROOM AT JOSE L. BASA MEMORIAL SCHOOL,

KATULAD NITO

Mga kaugnay na proyekto

Parehong bayan o parehong uri ng gawain, pinakamalaking published na budget muna.

Source: DPWH Infrastructure Transparency Dataset via BetterGov Open Data (CC0). Ang bayan ay hinuhulaan mula sa coordinates at pamagat. Balik sa lahat ng proyekto.

Tulungan kaming buuin ang site na ito

Ang site na ito ay ginawa at pinapanatiling updated ng mga volunteer mula sa Oriental Mindoro. Sabihin kung paano ka makakatulong.

Gagamitin lang namin ang detalye mo para kontakin ka tungkol sa pagba-volunteer.